  1. [verwijderd] 18 november 2021 14:50
    www.ivanhoemines.com/site/assets/file...

    Kamoa Copper awards China Nerin Engineering contract for
    direct-to-blister copper smelter
    ¦
    500-ktpa smelter to be the largest copper smelter in Africa, and
    one of the world’s largest single-line smelters
    ¦
    Metso Outotec’s state-of-the-art, environmentally-friendly
    smelter technology aligned with Kamoa-Kakula’s goal of
    producing the world’s ‘greenest copper’
  2. forum rang 10 DeZwarteRidder 9 december 2021 14:51
    quote:

    easy56 schreef op 9 december 2021 13:26:

    ceo.ca/@newsfile/kamoa-kakula-phase-2...

    Kamoa-Kakula Phase 2 Expansion Now 70% Complete, on Track for Early Start-up in Q2 2022

    vimeo.com/654809393/8ca99b13e3
    Complete, on Track for Early Start-up in Q2 2022

    Record copper production in November tops 18,270 tonnes, bringing year-to-date production to more than 87,000 tonnes as at November 30, 2021

    Earthworks commenced for a new box cut to access Phase 3 mining areas; Phase 3 concentrator targeted by end of 2024

    Engineering for Kamoa Copper's direct-to-blister smelter underway; long-lead items for smelter to be ordered in Q2 2022

    Mining crews deliver a record 548,000 tonnes of ore grading 5.46% copper in November, including 362,000 tonnes grading 6.60% copper from the centre of the Kakula Mine

    Record mining production in November increases surface stockpiles to 3.92 million tonnes grading 4.64% copper, containing more than 181,000 tonnes of copper

    Kolwezi, Democratic Republic of Congo--(Newsfile Corp. - December 9, 2021) - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng "Miles" Sun announced that Kamoa-Kakula's Phase 2, 3.8 million-tonne-per-annum (Mtpa) concentrator plant now is approximately 70% complete and is well on track to begin operations in Q2 2022.

    As the Phase 1, 3.8-Mtpa concentrator plant is operating at steady-state design capacity, further production updates will be provided only on a quarterly basis. Ivanhoe's 2021 production guidance for contained copper in concentrate produced from Kamoa-Kakula's Phase 1 concentrator is 92,500 to 100,000 tonnes. The higher guidance numbers are reinforced by an excellent production performance in November, which saw a record 18,270 tonnes of copper in concentrate produced, bringing year-to-date output to more than 87,000 tonnes as at November 30, 2021. The figures are on a 100%-project basis and metal reported in concentrate is prior to refining losses or deductions associated with smelter terms.

    Watch the latest video showcasing the expansion work underway at the Kamoa Copper Complex: vimeo.com/654809393/8ca99b13e3

    Kamoa-Kakula's 2021 copper production to the end of the year, as well as guidance for 2022 copper production, cost of sales and cash costs, including the start of Phase 2 operations, will be provided in January 2022.

    357,000 tonnes of ore were milled in November at an average feed grade of 6.18% copper, exceeding the monthly design run rate of 316,667 tonnes by more than 12%.

    Copper flotation recoveries averaged 85.4% in November. The Phase 1, steady-state design copper recovery is approximately 86%, depending on ore feed grade.